Forane Removal Project

Forane Removal Project

15 Sep

PT. Eskimo Wieraperdana participate in awareness of potential depletion of ozone (Ozone depletion Potential, ODP) with the executor to transfer B3 wastes in the form of refrigerant contaminated natural gas in the platform Handil belonging to TOTAL E & P Indonesia, Balikpapan. Refrigerant if directly released into nature will potentially damage the ozone layer of the earth, Refrigerant much as 42 tons were transferred to ISO tank capacity of 40 tons by 2 tanks and then sent to the extermination facility owned by PT. Holcim Indonesia in Gunung Puteri, Bogor. Removal process using tools and instruments that have been certified as well as equipment-zone 1 and zone 2 (Explosion proof). Work contaminated refrigerant fluid transfer using a recovery pump is specially designed by a team of engineering Eskimo. At Holcim, refrigerant destroyed by fire with burner cement at temperatures of 2000 ° C in order to decompose and be absorbed back into nature safely.